| - |
Mobil Producing Nigeria, the objective was a smokeless flare. |
| - |
Seaweld were awarded the full EPC project with a value to $2.9m. |
| - |
In-house design, procurement and construction was effected against a very tight timescale. |
| - |
Timely and successful completion was hailed by MPN as a major technical and political achievement. |
| - |
Members of the design team went on to supervise the project on site. |
| - |
New installations included:
- 10 ft x 60ft knockout drum
in the 48" gas line
- extensive air ducting
- two additional flare tips |
| - |
The project extended to all civils work including the removal and replacement of the bundwall. |
| - |
A comprehensive recording system resulted in the Final Report being set up as a blue print for similar projects. |